Borland St Reconstruction Update #8

Courtesy of the City of Williams Lake:

Installation of water and storm mains was completed this week.

This coming week, curb, gutter and sidewalk along the project length will be installed, and base gravels will be placed in preparation for paving.


The intersection of 4th Avenue and Borland Street will remain closed until further notice, due to unforeseen additional work that must be completed.


The project remains on schedule, with paving expected during the last week of September.